Below is our new, more informative bond report format. You made the impossible happen, so we are committed to ensuring that everyone knows as much as possible about our bond progress. 


Progress Corner 

June 2019:

EISENHOWER MIDDLE SCHOOL MAJOR 2017 FACILITY BOND PROJECTS 

-25% Complete 

-CMU continues to be laid (West side of Area “B”) 

-Decking installation beginning soon -Storm drain piping being installed in Gym D106 

-Furniture 35% design review 

SAFE ROOMS (*PHASE 1) 

-Almor West Substantial Completion 

-Carriage Hills 99% 

-Crosby Park Substantial Completion 

-Edison Substantial Completion 

-Hugh Bish Substantial Completion 

-Sullivan Village 99% 

-Woodland Hills Substantial Completion

-Whittier GMP recommendation


A few Extras to Note:

  • The district is on the fastest schedule legally possible to ensure that EMS and Safe Rooms start as ASAP! It takes MONTHS to get these things in place, but we are not wasting a day to ensure that we break ground in the Spring – as promised -- (Please see: Toby Dawn the Christmas Elf)
  • We had the LAWTON CAN Page to share information (it is still there, to keep us honest), but we have added the LAWTON SIP Page to store all updates and information as we move forward.

District staff members have worked extremely hard to move as fast as possible. We owe it to you to deliver on this bond and to keep you informed.  (*View SIP Project Updates)